HS2 – How Weak Commercial and Contract Management Contributed to Billions in Cost Overruns

How does a major infrastructure project end up costing almost twice its previous estimate?

HS2 provides a powerful lesson in the financial consequences of inadequate commercial controls, scope management and contract administration.

In 2026, the National Audit Office reported that the estimated cost of completing HS2 had risen to between £87.7 billion and £102.7 billion, approximately double the 2020 estimate for Phase One.

The NAO identified scope changes, inefficient delivery and underestimated delivery times among the principal causes. It also reported that HS2 had lacked important delivery and contract management skills.

One particularly revealing finding was that HS2 hoped to avoid approximately £2 billion in future costs through commercial renegotiation and improved supplier incentives.

NAO press release

What went wrong?

The case highlights several issues familiar to experienced contract managers:

A signed contract does not guarantee cost certainty.

Effective contract management requires disciplined change control, early warning procedures, reliable cost forecasting, supplier performance monitoring and commercial negotiation throughout the contract life cycle. The HS2 experience demonstrates why commercial competence must continue well beyond contract award.