The Edinburgh Tram Inquiry offers a clear warning to anyone buying major construction work: do not rely on a fixed price if the design and other assumptions behind that price are still changing.
The original Edinburgh tram project opened late and delivered a shorter route than planned. The inquiry reported a cost of £776.7 million for that restricted route, compared with a £545 million budget. Lord Hardie’s inquiry report identified several causes. One was the decision to sign the main infrastructure contract while the design remained incomplete.
For procurement and commercial managers, the lesson is practical. Before contract award, can both parties identify what the contractor has priced, what remains uncertain and who will bear the cost if assumptions change?
What did the Edinburgh Tram Inquiry find?
The procurement strategy depended on design progressing far enough to support the infrastructure contractor’s price. It also assumed that necessary approvals would be obtained and utilities would be diverted before the relevant construction work began.
Those assumptions were not met. The inquiry found that the design was incomplete when the infrastructure contract was signed. Subsequent design development was therefore likely to be treated as a change under the contract. The inquiry concluded that signing at that stage departed from the procurement strategy and failed to transfer design risk to the extent assumed in the final business case.
This was not the project’s only problem. The inquiry also examined delays, governance, reporting and the management of utilities. But incomplete design made the promised certainty over price much harder to achieve.
Why does an incomplete scope put a fixed price at risk?
A contractor can price defined work. It cannot give the same price certainty for decisions that have yet to be made.
When design, approvals or site information remain unresolved, the parties need to understand the effect on the agreed scope. Otherwise, later work may prompt variations, delay claims and disputes about who accepted the risk.
Calling a contract “fixed price” does not settle those questions. The contract must explain what the price includes, which assumptions support it and how changes will be valued.
Five scope checks before contract award
1. Confirm design maturity. Which drawings and specifications are approved? Which are still developing, and when will they be ready?
2. Record approvals and dependencies. Identify the consents, access arrangements and utility diversions needed for the contractor to proceed. Give each task an owner and a realistic date.
3. Test the pricing assumptions. Ask the contractor to identify exclusions, provisional sums and areas where its price depends on information still to come.
4. Make risk allocation explicit. State who bears the time and cost consequences if an assumption proves wrong. Do not assume that a contract label has transferred the risk.
5. Revisit the business case if the facts change. Lord Hardie recommended delaying negotiations where the business case assumes design, approvals or utility diversions will be complete before award. If those assumptions cannot be met, the project should prepare and approve a new business case before signing.
The lesson for commercial managers
The Edinburgh Tram Inquiry does not mean every drawing must be final before any construction contract can be signed. It does show the danger of signing on the basis of one level of design maturity while the project is actually at another.
A sound scope of work tells the parties what will be delivered, what information is still outstanding and how they will manage change. That gives the buyer a firmer basis for evaluating price and the contractor a clearer basis for delivery.