The Birmingham Oracle project offers a warning for any organisation replacing a major IT system: a software specification must describe the work the organisation needs to do, the data it needs to move and the tests that will prove the new service is ready.
Birmingham City Council planned to replace its ageing SAP system with Oracle Fusion. The original capital allocation was about £19 million. In January 2026, the council reported a total forecast of £144.4 million through 2027/28. That larger figure covers more than the initial implementation: it includes work to fix the first system, re-implementation, support and running costs. It is a serious increase, although the two figures are not directly comparable.
The first system went live in April 2022. An independent public interest report later identified problems with requirements, solution design, testing and the go-live decision. The lesson for buyers is not that one defective specification explains everything. It is that unclear requirements can leave a major programme exposed throughout its life.
What went wrong with the Birmingham Oracle project?
The independent review found that the solution design was not fully frozen until two weeks before go-live. As a result, the programme lacked a sufficiently clear, agreed view of business requirements and how Oracle would meet them.
The council had intended to adopt standard Oracle functions where possible. In practice, it accepted significant customisation to align the new system with existing processes. That choice added dependencies between the council’s requirements and the technical solution.
Testing also presented a challenge. The review found limited evidence that decision-makers adequately challenged the results or considered whether late design changes had left enough time for testing. They therefore made the go-live decision without a sound understanding of the system’s condition and the risks they were accepting.
These findings offer five practical lessons for anyone developing an IT specification.
Five lessons for better IT project specifications
1. Define the outcome before choosing the solution. Start with the services users must be able to complete. For a finance system, that might include paying suppliers, reconciling income and producing reliable accounts. Describe how you will test each outcome.
2. Challenge requests for customisation. An old process may exist because an old system required it. Before specifying bespoke development, ask whether the new product’s standard process can deliver the required outcome. Record the cost, benefit and long-term support needs of each exception.
3. Treat data migration as a deliverable. Identify what data must move, who will clean and validate it, and how the buyer will confirm that records are complete and usable. A new system cannot work reliably with data that the organisation has not prepared.
4. Set clear acceptance criteria before go-live. State which end-to-end tasks must pass testing, who signs them off and what happens if critical defects remain. A launch date is not evidence that a system is ready.
5. Give the buyer the capacity to challenge. Technical and commercial managers need enough knowledge to question supplier assumptions, assess proposed changes and understand the effect on cost and delivery. The specification should also make responsibilities clear on both sides.
The commercial lesson
The Birmingham Oracle project shows why specifications need to be managed after they are written. Requirements, design decisions, testing evidence and changes must remain connected. Otherwise, teams can approve development activity without proving that the finished system delivers the service they need.